Free resource library

Template Module 03

Equipment Maintenance and Inspection Log

A per-machine record: the start of shift inspection the regulations require, the service intervals the manufacturer requires, and the repair history that tells you what a machine is really costing you.

Who it is for. Anyone who has sold a machine and been unable to prove it was serviced, or has argued with an insurer or a warranty department about a failure.

Download the PDF US Letter. Printable. Free.

This sheet ladders into module 03, What Your Machine Actually Costs You.

Three reasons to keep this, in order of how much they are worth

First, the start of shift check is required. 1926.601(b)(14) requires vehicles in use to be checked at the beginning of each shift, and 1926.602 covers earthmoving equipment specifically. The log is how you prove the check happened.

Second, the service record is what a warranty claim and a resale both stand on. A machine with a complete log sells for more than the identical machine without one, and it is the same machine.

Third, and this is the one that pays for the sheet, the repair history is the data behind your operating cost per hour. Guessing at repair cost is guessing at your rate. A year of this log turns that guess into a number.

Machine record

  • Unit number
  • Make and model
  • Year
  • Serial or PIN
  • Engine make and model
  • Meter type: hours or miles
  • Date acquired
  • Meter at acquisition
  • Warranty expiry: date and meter
  • Filter part numbers
  • Fluid capacities and specifications

Start of shift walkaround

Tick it, initial it, date it. The defect column is the point of the exercise.

  • Engine oil, coolant, hydraulic and fuel levels
  • Leaks under the machine and on the ground where it sat
  • Tracks or tires: tension, wear, damage, missing pads or lugs
  • Undercarriage: rollers, idlers, sprockets, guards
  • Bucket, teeth, cutting edge, pins and bushings
  • Hoses, fittings and cylinder rods for damage or weeping
  • Belts, hoses and the radiator or cooler pack for debris
  • Grease points, per the manufacturer's interval
  • Air filter restriction indicator
  • Cab: mirrors, glass, wipers, horn, backup alarm, lights, beacon
  • Seat belt and ROPS structure undamaged, 1926.602(a)(2)
  • Fire extinguisher present, charged and in date
  • Steps, handholds and access points clean and unobstructed
  • Controls and safety devices function correctly
  • Defects recorded and reported before the machine is placed in service, 1926.601(b)(14)

Scheduled service log

Intervals come from the manufacturer's operation and maintenance manual, not from this sheet and not from habit.

DateMeterService performedInterval it satisfiesParts and fluids usedPerformed byCost

Repair log

Everything that was not scheduled. This is the column that tells you when a machine has turned into a hobby.

DateMeterFailureCause, if knownPartsLabour hoursDowntime hoursCost

Downtime hours matter as much as cost. A thousand dollar repair that cost you three days in the middle of a job was not a thousand dollar repair.

Wear measurement log

Undercarriage, tires and ground engaging tools, measured rather than guessed, so you can prorate them properly on your cost worksheet.

DateMeterComponentMeasurementPercent wornEstimated hours remaining

Fluid sample log

If you sample oil, record it here. If you do not, this table is the argument for starting.

DateMeterSample typeLabResultAction taken

The truck and trailer that move it

Different rules apply to the vehicle, and they are federal.

  • Driver vehicle inspection report completed as required, 49 CFR 396.11
  • Defects reported and repaired before the next dispatch, 49 CFR 396.11
  • Annual inspection current
  • Cargo securement checked against 49 CFR Part 393 Subpart I before every move
  • Tiedowns rated, in good condition, and enough of them for the working load
  • Attachments secured separately from the machine
  • Permits for oversize or overweight loads on board
  • Route checked for bridges, weight limits and overhead clearance

Where this comes from

Every code, standard and statute this sheet leans on, with a link to the body that publishes it. Check them. That is what they are for.